A project plan includes the Work Breakdown Structure (WBS) and cost estimates. Which of the
following are the parts of a project plan?
Each correct answer represents a complete solution. Choose all that apply.
A.
Risk identification
B.
Project schedule
C.
Risk analysis
D.
Team members list
E.
Security Threat
Explanation: