Which risk response will likely cause a project to use the procurement processes?

You work as a project manager for BlueWell Inc. You are working with your team members on the
risk responses in the project. Which risk response will likely cause a project to use the
procurement processes?

You work as a project manager for BlueWell Inc. You are working with your team members on the
risk responses in the project. Which risk response will likely cause a project to use the
procurement processes?

A.
Mitigation

B.
Sharing

C.
Exploiting

D.
Acceptance

Explanation: