You are a project manager in charge of a project to launch an e-commerce site. One team
member repeatedly implements additions to the site that do not comply with the original design
specifications. Which of the following best describes this situation?
A.
The team member is helping to develop the e-commerce site.
B.
The team member is helping to pilot the project.
C.
The team member is introducing scope creep.
D.
The team member is contributing valuable information that was omitted from the original
specifications.