You are the project manager in change of a project to launch an e-commerce site. Over the course of the project, several unforeseen issues arose, and the team implemented additions that were not included in the original design specifications. The project was completed three month after the original deadline.
Which of the following best describes this situation?
A.
The project experienced scope creep.
B.
The project quality control measures failed.
C.
The project was implemented according to plan.
D.
The original project design specifications were wrong.