As a project manager, you have to balance three elements that compose the project
triangle. Suppose your customer requests that you add some new requirements to the
project when you are halfway through. If you agree to this request, how would it affect other
aspects of the project?
A.
Cost of the project will increase.
B.
Cost of the project will decrease.
C.
Time to complete project will be reduced.
D.
Project scope will decrease.