Using Oracle Scheduler you have scheduled two jobs, JOB_A and JOB_B, to run at
9:00 p.m. every Friday. You want both the jobs to use a single resource plan,
WEEKEND_PLAN.
Which task must have already been performed to enable you to achieve this objective?
A.
A window must have been created with the WEEKEND_PLAN resource plan.
B.
A program must have been created with the WEEKEND_PLAN resource plan.
C.
A job class must have been created with the WEEKEND_PLAN resource plan.
D.
A windows group must have been created with the WEEKEND_PLAN resource plan.