You have set up a project in Microsoft Office Project Server 2007 in which your resources report their tasks by actual work and remaining work. You need to review and approve these changes in Microsoft Office Project Web Access. What should you do?

You have set up a project in Microsoft Office Project Server 2007 in which your resources report their tasks by actual work and remaining work. You need to review and approve these changes in Microsoft Office Project Web Access. What should you do?

A.
On the Administrative Time page, accept administrative time.

B.
On the Task Updates page, accept task updates.

C.
On the Timesheet Approvals page, approve timesheets.

D.
On the My Timesheets page, save updates.