You need to configure Microsoft Office Project Server 2007 to enable a resource manager to enter task updates for a new resource that will not log in to Project Web Access.
You add the new work resource. What should you do next?
A.
Select the resource manager for the RBS field.
B.
Select the resource manager for the Default Assignment Owner field.
C.
Enable the Team Assignment Pool option. Select the resource manager for the Team Name field.
D.
Select the resource manager for the Timesheet Manager field.