A project is undertaken for a customer where all labor costs are non-billable, and Non-Labor costs
are billable if the accumulated costs incurred are greater than $10k.
How can Oracle Projects be implemented to support this?
A.
Use transaction controls to restrict billing to Non-Labor elements and to calculate the bill
amounts on Non-Labor.
B.
Use transaction controls tobilling Non-Labor elements, capture the value on the project, and
then use the Non-Labor billing extension to calculate when an activity is billable.
C.
Create an agreement and funding for $10k only, and fund only those tasks on a project where
you estimate to incur costs of $10k or more.
D.
Use the cost-to-cost billing extension to build billing rules to meet the requirement.
E.
Use the cost accrual extension.