Company ABC wants to deploy workplan task structures where the lowest tasks represent
deliverables. They want to collect costs at a level higher than the lowest tasks for groups of
deliverables. Which two task structure relationships are available for them to consider?
A.
Define the structures as Fully Shared.
B.
Utilize Task-based mapping structures.
C.
Defineaseparate branch of task hierarchy for deliverables.
D.
Define a separate branch of task hierarchy for cost collection.
E.
Definethe structures as Partially shared.
Explanation:
Note:
*You can set up two types of project structures in Oracle Projects:
/Workplan structures consist of tasks that help project managers and team members plan, track,
and deliver projects on time.
/Financial structures consist of tasks that help project managers and financial administrators track
billing, costs, budgets, and other financial information for individual projects.
*If you enable both a workplan structure and a financial structure for your project or project
template, you can decide whether or not they are integrated, and if so, to what degree. You do this
by choosing one of the following options on the Structures setup page:
/Shared Structures: Enables you to generate a financial structure with a task hierarchy that is fully
shared by the workplan structure task hierarchy. Workplan and financial structures are fully shared
by default.
/Partially Shared Structures: Enables you to generate a financial structure that is partially shared
by the workplan structure hierarchy.
/Non-Shared: Task-Based Mapping: Enables you to map individual workplan structure tasks to
individual financial structure tasks.
/Non-Shared: No Mapping: Choose this if you do not want to integrate your project workplan and
financial structures in any way.