You have defined a Non-Labor resource “Mini Truck” with an expenditure type “Vehicle” that has
a rate of $100. This resource is attached to three Non-Labor resource organizations:
“Construction-East,” “Construction-West,” and “Construction-Central.”
How do you set up a rate of $150 for usage charges when the “Mini Truck” owned by
“Construction-Central” is charged to a project?
A.
In the Project setup, enter a rate of $150 for”Construction-Central”in the organization overrides.
B.
In the Non-Labor resources setup, select the”Construction-Central”organization and enter a
rate of $150.
C.
Create a new rate schedule with a rate of $150 for”Mini Truck”and attach it to the project.
D.
Create a new rate schedule with a rate of $150 for”Mini Truck”and attach it to”ConstructionCentral.”
E.
Write custom code in Non-Labor cost override extension.