Select the two options required to ensure that this change is reflected in the existing assignment on resource calendars.

A one-time additional public holiday has been announced for this year. You update the PA
Calendar, which is used for Resourcing with this exception. Select the two options required to
ensure that this change is reflected in the existing assignment on resource calendars.

A one-time additional public holiday has been announced for this year. You update the PA
Calendar, which is used for Resourcing with this exception. Select the two options required to
ensure that this change is reflected in the existing assignment on resource calendars.

A.
Run”PRC: Generate CalendarSchedules.”

B.
Run “PRC: Rebuild Resource Timeline.”

C.
Inform Resource Managers that they will have to redo all the existing planning.

D.
Run “PRC: AutomatedCandidate Search.”

E.
Run “PRC:Refresh project summary amounts.”

Explanation:
Changes to these calendars impact the schedules of the person resources,
requirements, and assignments differently. Oracle Project Resource Management provides the
following administrative processes to help manage these changes and to maintain consistent
schedule information throughout the application:
PRC: Generate Calendar Schedule for a Single Calendar
PRC: Generate Calendar Schedules for a Range of Calendars

PRC: Rebuild Timeline for a Single Resource
PRC: Rebuild Timeline for a Range of Resources
Oracle Projects Fundamentals,Assigning People to Projects