A client requires a project definition that allows for charging expenditures to the project at a higher
Work Breakdown Structure level than where the manually entered percentage complete progress
is captured. Which three Shared Structure relationships will support this requirement?
A.
Shared
B.
Partially shared
C.
Mapped
D.
Not shared
E.
Vertical
Explanation:
Structure Integration Setup
If you enable both a workplan structure and a financial structure for your project or project
template, you can decide whether or not they are integrated, and if so, to what degree. You do this
by choosing one of the following options on the Structures setup page:
*Shared Structures: Enables you to generate a financial structure with a task hierarchy that is fully
shared by the workplan structure task hierarchy. Workplan and financial structures are fully shared
by default.
*Partially Shared Structures: Enables you to generate a financial structure that is partially shared
by the workplan structure hierarchy.
*Non-Shared: Task-Based Mapping: Enables you to map individual workplan structure tasks to
individual financial structure tasks.
*Non-Shared: No Mapping: Choose this if you do not want to integrate your project workplan and
financial structures in any way.
Oracle Projects Fundamentals