Which three statements are correct about defining a cost budget for a project?
A.
You can enterbudget amount atthe project level, the top task level, or the lowest task level.
B.
Youcan enterbudget amount only at the lowest task level.
C.
You can enterbudget amountfora combination of lowest task and a labor resource.
D.
Youcan enterbudget amount only at the top task level.
E.
You can enterbudget amount for a combination of lowest task and a Non-Labor resource.
F.
You cannot enterbudget amount for a combination of lowest task and a Non-Labor resource.
Explanation:
A:You can budget at the project, top task, or lowest task level.
Note:
*When you create budgets and forecasts that do not use budgetary control and budget integration
features, you can choose to enter budget and forecast amounts at any level of the financial
structure by selecting one of the following lowest level planning level options:
Project
Top Task
Lowest Task
When you choose the Lowest Task option, you can enter amounts at all levels of the financial
structure including top tasks, middle-level tasks, and lowest tasks. You can also enter amounts at
multiple task levels within the same branch of the financial structure. Oracle Projects treats
theamounts that you enter at each task level as incremental amounts that roll up into the total
amounts for the project.