Oracle Project Costing checks the control when the customer ________.

A customer enables transaction controls at the Project level. Oracle Project Costing checks the
control when the customer ________.

A customer enables transaction controls at the Project level. Oracle Project Costing checks the
control when the customer ________.

A.
transfers an expenditure item to another task of the same project

B.
runs the PRC: Distribute Labor Costs concurrent program

C.
runsthe PRC: Transaction Import concurrent program

D.
entersaproject-related invoice distributionin Oracle Payables

E.
enters an online or preapproved expenditureitem

Explanation:
Expenditure Item Validation
When you enter expenditure items, you are charging cost to a project and a task. Oracle Projects
validates expenditure items against predefined criteria and any transaction controls and
transaction control client extensions that you set up during the implementation.
Oracle Project Costing User Guide