You implement Project Manufacturing along with Project Costing for manufacturing company. You
define various expenditure types in which few are specific to Project Manufacturing. Identify the
three setups that are required to have an expenditure type specific to Project Manufacturing.
A.
Rate Required is enabled for theExpenditureType.
B.
“Work In Process” class is associated with the Expenditure Type.
C.
“Miscellaneous transactions” classis associated with the Expenditure Type.
D.
“Inventory” class is associated with the ExpenditureType.
E.
Rate Required Is not enabled for the Expenditure Type.
Explanation:
B:Work In Process – This expenditure type class is used for Project Manufacturing
WIP transactions that are interfaced from Manufacturing to Oracle Projects. You can also use thisexpenditure type class when you import other manufacturing costs via Transaction Import or when
you enter transactions via pre-approved batch entry.
D:Inventory – This expenditure type class is used for the following transactions:
Project Manufacturing transactions that are interfaced from Manufacturing or Inventory to Oracle
Projects.
Oracle Inventory Issues and Receipts that are interfaced from Oracle Inventory to Oracle Projects
in a manufacturing or non-manufacturing installation.
You can also use this expenditure type class when you import other manufacturing costs via
Transaction Import or when you enter transactions via pre-approved batch entry.
Note:
*If the Rate Required option for the selected expenditure type is enabled in Oracle Projects, then
you must enter a quantity. When you interface the invoice distribution toOracle Projects, Oracle
Projects copies the quantity and amount to the expenditure item and calculates the rate. If Rate
Required option for the selected expenditure type is disabled, then the quantity of the expenditure
item is set to the amount you enter in Oracle Payables.