A project manager wants to create a revenue budget based on the project agreement and
allocated funding. How can this be achieved?
A.
by manually creatingarevenue budget
B.
by selecting Funding revaluation in the systemimplementation options.
C.
by selecting the “baseline project without budget” option, which will createa revenue
budgetautomatically based on project funding
D.
by selecting Invoiceat top taskfor the project
E.
by setting transaction controls
Explanation:
You can automatically create and baseline an Approved Revenue Budget for a
project by checking the Baseline Funding without Budget check box in the Project Funding Inquiry
window.
Note:Budget/Fund/Bill at Project or Top Task Level
You can create a revenue budget, funding source allocation and project agreement, and perform
billing at either the project or the top task level. After you have created an allocation line at eitherlevel, you cannot change to another level. For example, if you have created a funding allocation
for a top task, you cannot create another funding allocation for the same project without entering a
top task.
Oracle Project Contracts Implementation Guide