You arc planning the tasks and timeline for an implementation of CRM On Demand The
implementation plan includes tasks for confirming business requirements, configuring and
customizing the application, developing reports, importing legacy data, and training administrators
and end users- In setting up your timeline, you want to make sure that tasks flow efficiently so that
you can meet your target date. At what point in the implementation timeline do you need to define
your data import requirements?
A.
As soon as application configuration is done and signed off by the business owners
B.
After training has been completed, to keep the data from being contaminated by training data
C.
Very near the start of the implementation, since this can Impact the project timeline,
configuration and training
D.
After validation is complete, so that the data Is current at go-live