Upper management has announced a change in a company’s primary hardware supplier for the
next year, the timing of this change coincides with key purchases that line of business department
has to make in support of its Java EE application upgrade/redesign project.
You are asked to help outline a strategy to preserve the project timeline and keep hardware
training costs contained.
Which recommendation will you make?
A.
Add new hardware to create a heterogeneous environment.
B.
Request another year of sales and support with the existing vendor.
C.
Request more time to consider the total cost of change to your project and to modify your
budget.
D.
Use new hardware on the web tier and redeploy existing hardware to the other tiers.
Explanation:
–
A
IF need to select 2 answer then A and D
Otherwise I would say D