Which set of steps is the recommended cabling sequence with FS1-2 hardware components?
A.
1. Pilot 1: Install CMA, plug all cables, and route them Power first, Ethernet Last.
2. Pilot 2: Same as above.
3. Controller 1: Install CMA, plug and route cables Power first, Ethernet, SAS Controller Interconnects,
SAS Controller to Strings and Front End Network Connections respectively.
4. Controller 2: Same as above.
5. DEs per string sequence.
B.
1. Controller 1: Install CMA, plug and route cablesPower first, Ethernet, SAS Controller Interconnects,
SAS Controller to Strings, and Front End Network Connections respectively.2.Controller 2: Same as above.
3.Pilot 1: Install CMA, plug all cables, and route them Power first, Ethernet last.
4.Pilot 2: Same as above.
5. DEs per string sequence.
C.
1. Controller 1: Install CMA, plug and route cables Power first, Ethernet,SASController Interconnects,
SAS Controller to Strings and Front End Network Connections respectively.
2. Controller 2: Same as above.
3. DEs per string sequence.
4. Pilot 1: Install CMA, plug al cablesand route them Power first, Ethernet Last.
5.Pilot 2: Same as above.
D.
1. Pilot 1: Install CMA, plug all cables,and route them Power first, Ethernet last.
2. Pilot 2: Same as above.
3. DEs per string sequence.
4. Controller 1: Install CMA, plug and route cables Power first, Ethernet, SAS Controller Interconnects,
SAS Controller to Strings, and Front End Network Connections respectively.
5. Controller 2: Same as above.