You have used orchestrations to specify security lists, security rules, security IP lists, IP reservations, and
storage volumes. You are now creating instances.
Which three relationships (dependencies) must you define to ensure that the entire topology can be started
and stopped without errors?
A.
from instances to IP reservation
B.
from instances to security rules
C.
from instances to storage volumes
D.
from security IP lists to security rules
E.
from security rules to security lists
Explanation:
https://docs.oracle.com/cloud/latest/stcomputecs/STCSG/GUID-6CB9D494-4F3C-4B78-BD03-
127983FEC357.htm#GUID-6CB9D494-4F3C-4B78-BD03-
127983FEC357__RELATIONSHIPSBETWEENORACLECOMPUTECL-A9E9FFD8
ACE
A C E
https://docs.oracle.com/en/cloud/iaas/compute-iaas-cloud/stopc/creating-instances.html
ACE
A,C,E