An administrator sets the Failover Capacity for both CPU and Memory at 25%.
Based on the Exhibit below, how much of the cluster’s total CPU resources are still available to power on
additional virtual machines?
A.
45%
B.
25%
C.
70%
D.
60%
Explanation:
https://pubs.vmware.com/vsphere-50/index.jsp?topic=%2Fcom.vmware.vsphere.avail.doc_50%
2FGUID-FAFEFEFF-56F7-4CDF-A682-FC3C62A29A95.html
A
Current load 7/24*100 = 29% -> about 30%
Failover capacity set to 25%.
Available capacity: 100-(25+30) = 45%