You are working on a hybrid cloud project, where production applications (yet to be fully
developed) are to be deployed. Which of the following is a project requirement?
A.
The production data must be in the UK at all times.
B.
The hosting partner provides sufficient resources without overcommitment to support
application load.
C.
The hosting provider meets uptime expectations.
D.
The development team provides the software on time.
Explanation:
A requirement is a definable and measurable project item. It must be part of the delivery, and
itsremoval cannot be justified.
Chapter 2, Definitions of Key Terms