You are a technical consultant designing a solution for an online retail company. The project vision
is to deploy a hybrid cloud, with the internal team developing the website on internal infrastructure
and migrating production-ready applications to a hosting provider. The project is expected to ease
deployment and require less infrastructure capital expenditure—without lowering application
quality.
Which of the following is a risk to the project?
A.
The solution must adhere to ISO 27001.
B.
Change control of the hosting vCloud platform is not under full control of the internal business.
C.
The hosting provider outsources the platform support to the platform vendor.
D.
The applications to be deployed on the production hosts are not fully developed, although a
beta exists.
Explanation:
The technical design process enables the platform designer to work in a methodical way and
withothers who have similar objectives. A risk is that a project item could potentially prevent the
vision or aspectsof it (requirements) from being created.
Chapter 1, The Technical Design Process