You are a VMware consultant working at a small managed services company. The company has
won a contract with a large company, Company A, to host its test and dev platform, with the
chance on annual review to host the production platform.
Although you have been engaged early in the project due to business requirements, the budget for
the project has already been combined with that for another DR project for another company,
Company B. The thought process for this decision is that, if needed, the test systems from
Company A have a lower requirement in the unlikely event of Company B having a DR event.
All the items have been bought and are to be delivered. Your role is to take the equipment
provided and construct, develop, and implement a scalable working vSphere platform. The
following requirements are stated:
Company A test machines must be provided with sufficient resources for BAU.
Company B systems can be made available with minimum impact to Company A.
For Company A, RTO is 7 days, and RPO is 1 month.
For company B, RTO is 1 hour, and RPO is 15 minutes.
Using a shared infrastructure in this way is a risk to the project.
A.
True
B.
False
Explanation:
The technical design process enables the platform designer to work in a methodical way and
withothers with similar objectives. A risk is an object that could prevent the delivery of the project
requirements.
Chapter 1, The Technical Design Process