The difference between the beginning of a project and the vision is also known as the ____________.

The difference between the beginning of a project and the vision is also known as the
____________.

The difference between the beginning of a project and the vision is also known as the
____________.

A.
current state analysis

B.
gap state analysis

C.
upstream relationship

D.
downstream relationship

Explanation:

By reviewing the current configuration of a system and mapping the final status of components
asdescribed in the vision, the business identifies the gap between the two. A gap state analysis is
a review of theitems or tasks that are required to progress between the stages. Such an analysis
is useful in creatingmilestone plans, implementation orders, and so on.