An implementation plan should contain _____________.

An implementation plan should contain _____________.

An implementation plan should contain _____________.

A.
a milestone plan

B.
risks, assumptions, and dependencies on the activities in the implementation plan

C.
order

Explanation:

An implementation plan gives all members of a project team a level of understanding of

thetechnical approach of a project, the number of phases, major tasks in each phase, and the
correct order forcompleting the tasks.