(Choose two)

You are VMware architect working at a large enterprise where a new VMware platform is being
installed.
Based on conversations with the business, you establish that the RTO requirement is 8 hours, and
the RPO requirement is 15 minutes. After months of successful use, the system crashes at 4 p.m.
To meet the project SLA, _____________. (Choose two)

You are VMware architect working at a large enterprise where a new VMware platform is being
installed.
Based on conversations with the business, you establish that the RTO requirement is 8 hours, and
the RPO requirement is 15 minutes. After months of successful use, the system crashes at 4 p.m.
To meet the project SLA, _____________. (Choose two)

A.
the application must be brought online and be accessible to users by midnight.

B.
the application must be brought online and be accessible to users by 4:15 p.m.

C.
when the application is brought online the data must be from a version as of 3:45 p.m.

D.
when the application is brought online the data must be from a version as of 8 p.m. the night
before.

Explanation:

The recovery time objective (RTO)—also known as the return to operation—is the amount of timeit
takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the
point intime to which the system needs to be restored following a failure.