Which of the following steps is the least disruptive option that can be taken to prepare for the maintenance event?

An administrator must perform maintenance on a fibre channel switch connected to vmhba2 on an ESX host. The ESX host has been configured with the Fixed policy, and the preferred path will be impacted by the maintenance event. Which of the following steps is the least disruptive option that can be taken to prepare for the maintenance event?

An administrator must perform maintenance on a fibre channel switch connected to vmhba2 on an ESX host. The ESX host has been configured with the Fixed policy, and the preferred path will be impacted by the maintenance event. Which of the following steps is the least disruptive option that can be taken to prepare for the maintenance event?

A.
Change the policy on the ESX Host to MRU for the duration of the maintenance event

B.
Use the vSphere Client to disable the path impacted by the maintenance event

C.
Unplug the FC cable from vmhba2 for the duration of the maintenance event

D.
Unplug the FC cable from the Storage Processor port on the FC array for the duration of the maintenance event