A Pay-As-You-Go Organization vDC just ran out of resources. The resource pool backing the
Provider vDC is fully consumed, but the cluster has no more resources to spare and is at its
maximum size. Which two actions should the administrator perform to allocate more resources to
the Organization vDC? (Choose two.)
A.
Change the setting on the resource pool backing the Provider vDC to Unlimited.
B.
Add a second cluster to the Provider vDC.
C.
Add a resource pool to the Provider vDC from another cluster.
D.
Add another Organization vDC backed by a different Provider vDC to the Organization.
I believe correct answer is B C.
B because default resource pool we will be adding to Provider VDC
C because we can add any custom resource pool from another cluster.
D will not add more resources to existing org VDC and question is about adding to the resources org vdc.
D is incorrect.