Which of the following processes is described in the statement below?
“This is the process of numerically analyzing the effect of identified risks on overall project
objectives.”
A.
Identify Risks
B.
Perform Qualitative Risk Analysis
C.
Perform Quantitative Risk Analysis
D.
Monitor and Control Risks
Explanation: