The process of removing the extra features to remove the risks is called what?

Beth is a project team member on the JHG Project. Beth has added extra features to the project
and this has introduced new risks to the project work. The project manager of the JHG project
elects to remove the features Beth has added. The process of removing the extra features to
remove the risks is called what?

Beth is a project team member on the JHG Project. Beth has added extra features to the project
and this has introduced new risks to the project work. The project manager of the JHG project
elects to remove the features Beth has added. The process of removing the extra features to
remove the risks is called what?

A.
Corrective action

B.
Preventive action

C.
Scope creep

D.
Defect repair

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *