Where can Mark determine the priority of a risk given its probability and impact?

Mark is the project manager of the BFL project for his organization. He and the project team are
creating a probability and impact matrix using RAG rating. There is some confusion and
disagreement among the project team as to how a certain risk is important and priority for attention
should be managed. Where can Mark determine the priority of a risk given its probability and
impact?

Mark is the project manager of the BFL project for his organization. He and the project team are
creating a probability and impact matrix using RAG rating. There is some confusion and
disagreement among the project team as to how a certain risk is important and priority for attention
should be managed. Where can Mark determine the priority of a risk given its probability and
impact?

A.
Risk response plan

B.
Look-up table

C.
Project sponsor

D.
Risk management plan

Explanation: