what type of risk response?

Gary has identified a project risk that could injure project team members. He does not want to
accept any risk where someone could become injured on this project so he hires a professional
vendor to complete this portion of the project work. This workaround to the risk event is known as
what type of risk response?

Gary has identified a project risk that could injure project team members. He does not want to
accept any risk where someone could become injured on this project so he hires a professional
vendor to complete this portion of the project work. This workaround to the risk event is known as
what type of risk response?

A.
Avoidance

B.
Mitigation

C.
Acceptance

D.
Transference

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *