Fred is the project manager of the PKL project. He is working with his project team to complete the
quantitative risk analysis process as a part of risk management planning.
Fred understands that once the quantitative risk analysis process is complete, the process will
need to be completed again in at least two other times in the project. When will the quantitative
risk analysis process need to be repeated?
A.
Quantitative risk analysis process will be completed again after the risk response planning and
as a part of monitoring and controlling.
B.
Quantitative risk analysis process will be completed again after the plan risk response planning
and as part of procurement.
C.
Quantitative risk analysis process will be completed again after new risks are identified and as
pa of monitoring and controlling.
D.
Quantitative risk analysis process will be completed again after the cost management planning
an as a part of monitoring and controlling.
Explanation: