which of the following are likely to increase?

You work as a project manager for BlueWell Inc. There has been a delay in your project work that
is adversely affecting the project schedule. You decided, with your stakeholders’ approval, to fast
track the project work to get the project done faster. When you fast track the project which of the
following are likely to increase?

You work as a project manager for BlueWell Inc. There has been a delay in your project work that
is adversely affecting the project schedule. You decided, with your stakeholders’ approval, to fast
track the project work to get the project done faster. When you fast track the project which of the
following are likely to increase?

A.
Costs

B.
Risks

C.
Human resource needs

D.
Quality control concerns

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *