You are the project manager of the NNN project for your company. You and the project team are
working together to plan the risk responses for the project. You feel that the team has successfully
completed the risk response planning and now you must initiate what risk process it is. Which of
the following risk processes is repeated after the plan risk responses to determine if the overall
project risk has been satisfactorily decreased?
A.
Risk response implementation
B.
Quantitative risk analysis
C.
Risk identification
D.
Qualitative risk analysis
Explanation: