You are the project manager for your company and a new change request has been approved for
your project. This change request, however, has introduced several new risks to the project. You
have communicated these risk events and the project stakeholders understand the possible
effects these risks could have on your project. You elect to create a mitigation response for the
identified risk events. Where will you record the mitigation response?
A.
Risk log
B.
Risk management plan
C.
Risk register
D.
Project management plan
Explanation: