what term?

You work as a project manager for BlueWell Inc. Your project is using a new material to construct
a large warehouse in your city. This new material is cheaper than traditional building materials, but
it takes some time to learn how to use the material properly. You have communicated to the
project stakeholders that you will be able to save costs by using the new material, but you will
need a few extra weeks to complete training to use the materials. This risk response of learning
how to use the new materials can also be known as what term?

You work as a project manager for BlueWell Inc. Your project is using a new material to construct
a large warehouse in your city. This new material is cheaper than traditional building materials, but
it takes some time to learn how to use the material properly. You have communicated to the
project stakeholders that you will be able to save costs by using the new material, but you will
need a few extra weeks to complete training to use the materials. This risk response of learning
how to use the new materials can also be known as what term?

A.
Cost-benefits analysis

B.
Benchmarking

C.
Cost of conformance to quality

D.
Team development

Explanation: