Stephen is the project manager of the GBB project. He has worked with two subject matter experts
and his project team to complete the risk assessment technique. There are approximately 47 risks
that have a low probability and a low impact on the project.
Which of the following answers best describes what Stephen should do with these risk events?
A.
The low probability and low impact risks should be added to the risk register.
B.
Because they are low probability and low impact, the risks can be dismissed.
C.
Because they are low probability and low impact, Stephen should accept the risks.
D.
The low probability and low impact risks should be added to a watch list for future monitoring.
Explanation: