You are the project manager of the GHG project for your company. You have identified the project
risks, completed qualitative and quantitative analysis, and created risk responses. You also need
to document how and when risk audits will be performed in the project. Where will you define the
frequency of risk audits?
A.
Schedule management plan
B.
Risk management plan
C.
Quality management plan
D.
Risk response plan
Explanation: