You are the project manager of a computer upgrade project. You and the vendor are in dispute
over the deliverables the vendor was to provide and configure. What document can best describe
how you and the vendor are to proceed if there is a claim against the vendor?
A.
Procurement management plan
B.
Project cost management plan
C.
Enterprise environmental factors
D.
Contract
Explanation: