The water sanitation project manager has determined that risks associated with handling certain
chemicals are too high. He has therefore decided to allow someone else to complete this portion
of the project by outsourcing the handling and installation of the chemicals and filter equipment to
an experienced contractor. This is an example of which of the following?
A.
Transference
B.
Acceptance
C.
Mitigation
D.
Avoidance
Explanation: