Shawn is the project manager of the WHT Project for his company. In this project Shawn’s team
reports that they have found a way to complete the project work for less cost than what was
originally planned. The project team presents a new software that will help to automate the project
work. While the software and the associated training costs $25,000 it will save the project nearly
$65,000 in total costs. Shawn agrees to the software and changes to the project management plan
accordingly. What type of risk response has been used in this instance?
A.
Enhancing
B.
Accepting
C.
Avoidance
D.
Exploiting
Explanation: