Which of the following are the inputs to the identify risks process that Jeff will use to accomplish the task?

Jeff works as a project manager for BlueWell Inc. He is determining which risks can affect the
project. Which of the following are the inputs to the identify risks process that Jeff will use to
accomplish the task? Each correct answer represents a complete solution.
Choose all that apply.

Jeff works as a project manager for BlueWell Inc. He is determining which risks can affect the
project. Which of the following are the inputs to the identify risks process that Jeff will use to
accomplish the task? Each correct answer represents a complete solution.
Choose all that apply.

A.
Risk management plan

B.
Activity cost estimates

C.
Scope baseline

D.
Risk register

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *