.If an IS auditor observes that individual modules of a system perform…

.If an IS auditor observes that individual modules of a system perform correctly in development
project tests, the auditor should inform management of the positive results and recommend further:

.If an IS auditor observes that individual modules of a system perform correctly in development
project tests, the auditor should inform management of the positive results and recommend further:

A.
Documentation development

B.
Comprehensive integration testing

C.
Full unit testing

D.
Full regression testing

Explanation:
If an IS auditor observes that individual modules of a system perform correctly in development
project tests, the auditor should inform management of the positive results and recommend further
comprehensive integration testing.