Which of the following risks could result from inadequate software baselining?

Which of the following risks could result from inadequate software baselining?

Which of the following risks could result from inadequate software baselining?

A.
Scope creep

B.
Sign-off delays

C.
Software integrity violations

D.
inadequate controls

Explanation:

A software baseline is the cut-off point in the design and development of a system beyond which
additional requirements or modifications to the design do not or cannot occur without undergoing
formal strict procedures for approval based on a businesscost -benefit analysis. Failure to adequately
manage the requirements of a system through baselining can result in a number of risks. Foremost
among these risks is scope creep, the process through which requirements change during
development. ChoicesB , C and D may not always result, but choice A is inevitable.