which of the following?

Processing controls ensure that data is accurate and complete, and is processed only through which of the
following? Choose the BEST answer.

Processing controls ensure that data is accurate and complete, and is processed only through which of the
following? Choose the BEST answer.

A.
Documented routines

B.
Authorized routines

C.
Accepted routines

D.
Approved routines

Explanation:
Processing controls ensure that data is accurate and complete, and is processed only through authorized
routines.