Which of the following activities should the business c…

Which of the following activities should the business continuity manager perform FIRST after the replacement
of hardware at the primary information processing facility?

Which of the following activities should the business continuity manager perform FIRST after the replacement
of hardware at the primary information processing facility?

A.
Verify compatibility with the hot site.

B.
Review the implementation report.

C.
Perform a walk-through of the disaster recovery plan.

D.
Update the IS assets inventory.

Explanation:
An IS assets inventory is the basic input for the business continuity/disaster recovery plan, and the plan must
be updated to reflect changes in the IS infrastructure. The other choices are procedures required to update the
disaster recovery plan after having updated the required assets inventory.