The PRIMARY objective of testing a business continuity plan is to:

The PRIMARY objective of testing a business continuity plan is to:

A.
familiarize employees with the business continuity plan.

B.
ensure that all residual risks are addressed.

C.
exercise all possible disaster scenarios.

D.
identify limitations of the business continuity plan.

Explanation:
Testing the business continuity plan provides the best evidence of any limitations that may exist. Familiarizing
employees with the business continuity plan is a secondary benefit of a test. It is not cost effective to address
residual risks in a business continuity plan, and it is not practical to test all possible disaster scenarios.